Model Estimate for Loose Rock Dam Annually

Model Estimate for Loose Rock Dam Annually

1. Earth work in excavation for trench up to 0.30 in dept & width 2 m complete 0.30*4*2 =2.4m3
2. Providing and laying of stone
(i) For Dam 2*4*2 =16m3
(ii) For Apron 2*0.6*4 =4.8m3


Cost:

1. Cost of earth Work @ Rs.5.25/m3 2.4 * 25.00 = 60.00
2. Cost of stone work @ Rs.31.50/m3 20.8 * 116.00 = 2,412.80
3. Cost of wire net etc. L.S.   = 2,772.80
Add 3% contingency Rs.       83.18
Rs.   2855.98